EVALUATION OF PROJECT COST AND SCHEDULE PERFORMANCE USING THE EARNED VALUE MANAGEMENT (EVM) METHOD AND GAP ANALYSIS

EVALUASI KINERJA BIAYA DAN WAKTU PROYEK DENGAN METODE EARNED VALUE MANAGEMENT (EVM) DAN GAP ANALYSIS

Authors

  • deka yuda krisna permana 123
  • Hangga Prima Setiawan Universitas Islam Balitar
  • Heru Hendri Iswanto Universitas Islam Balitar

DOI:

https://doi.org/10.35457/quateknika.v16i02.5985

Keywords:

Cost, Earned Value Management, Project Performance, Schedule

Abstract

Schedule delays and cost overruns are common problems in construction projects. This study evaluates the cost and schedule performance of a three-story boarding house construction project in Blitar City, with a contract value of IDR 1,408,700,000, using Earned Value Management (EVM) and Gap Analysis. EVM was used to measure project performance and project cost and schedule completion, while Gap Analysis identified deviations and critical work items. At week 23, actual progress reached 80%, with an SPI of 0.80 and CPI of 0.73, indicating schedule delay and cost inefficiency. The projected EAC was IDR 1,929,726,027, with an EAS of approximately 29 weeks. Concrete and masonry works were identified as critical factors, contributing 52.25% of the project weight. After simulating corrective actions through weekly monitoring, additional personnel, and limited overtime, progress increased to 95%, with SPI and CPI reaching 0.95 and EAS decreasing to approximately 24.21 weeks. The results demonstrate that integrating EVM and Gap Analysis is effective for detecting project deviations and determining appropriate corrective actions. 

Downloads

Download data is not yet available.

References

[1] Aditama, R., & Witjaksana, B. (2021). Analisis biaya dan waktu menggunakan metode EVM

(Earned Value Method): Studi kasus pada proyek pembangunan Gedung Laundry RSUD

Sidoarjo.

[2] Annas, F. M., Solikin, M., Harnaeni, S. R., & Sunarjono, S. (2021). Evaluasi kinerja biaya dan

waktu pelaksanaan menggunakan metode Earned Value (EVM): Studi kasus Proyek

Pengendalian Banjir Kali Lamong.

[3] Asyiah, S., Maddeppungeng, A., & Alfalakh, D. S. (2020). Evaluasi kepuasan pelanggan

terhadap kinerja manajemen proyek kontraktor besar: Studi kasus Proyek Pembangunan

Kampus Untirta Sindangsari.

[4] Dharmawan, R. D., Safarizki, H. A., & Firdausi, A. A. (2023). Evaluasi efektivitas keputusan

addendum proyek terhadap waktu pekerjaan proyek berbasis Earned Value Method.

[5] Erik, D., Rodhi, N. N., Saputra, I. H., & Sholahuddin, M. (2025). Evaluasi kinerja biaya dan

waktu pada proyek jembatan menggunakan metode Earned Value: Studi kasus rehabilitasi

Jembatan Ngaglik Kedungadem-Kepohkidul Kabupaten Bojonegoro.

[6] Hayati, N. I., & Lugi, D. (2020). Evaluasi biaya dan waktu dengan metode Earned Value

Management: Studi kasus Ruko Damara Village, Kelurahan Ciparigi, Kota Bogor.

[7] Honesti, L., & Wiranto, R. (2021). Analisis pelaksanaan proyek konstruksi dengan metode

Earned Value pada pembangunan Hotel Santika Bukittinggi.

[8] Jatnika, A., & Johari, G. J. (2019). Analisis pengendalian waktu dengan Earned Value Concept

pembangunan Rumah Susun Jawa Barat 2 TA. 2019 Universitas Garut.

[9] Madeppungeng, A., Intari, D. E., & Fauziah, N. N. (2020). Evaluasi kepuasan pelanggan

terhadap kinerja manajemen proyek kontraktor besar: Studi kasus proyek pembangunan

Bendungan KLM di Provinsi Banten.

[10]Maulia, S., Maskur, A., & Hartati, G. (2025). Evaluasi pengendalian waktu menggunakan

metode Earned Value Management (EVM) pada pembangunan sarana dan prasarana Gedung

Pemuda Juara Kabupaten Pangandaran.

[11]Pasolang, R., & Mangngenre, S. (2025). Evaluasi kinerja proyek Feed End Shell Dryer

Replacement Process Plant PT. A menggunakan metode Earned Value Management.

[12]Purwanto, S., Mu’min, M. A., & Fernanda, A. (2021). Analisis nilai hasil terhadap waktu pada

proyek RS Hermina Kutabumi Tangerang.

[13]Putri, R. T., Damayanti, S., & Dofir, A. (2023). Analisis faktor penyebab keterlambatan

penyelesaian pada proyek Pembangunan Apartemen Urban Signature Ciracas.

[14]Rafi, M., & Hidayat, M. (2024). Evaluasi biaya dan waktu menggunakan metode EVM

(Earned Value Management).

[15]Rizki, Y., Imran, R. A., Muhammad, K., Kusuma, H. I., & Ridho, A. F. (2024). Usulan

penerapan Contractor Safety Management System pada tahap pra kualifikasi di PT. UES

menggunakan Gap Analysis.

[16]Rudiantoro, A. T. S. (2020). Evaluasi pengendalian biaya proyek peningkatan Jalan

Margaluyu Tahap II (DAK) dengan metode Earned Value Management (EVM).

[17]Sari, M. M., Hadi, T. S., & Aldiansyah. (2020). Faktor penyebab pembengkakan biaya yang

berpengaruh terhadap biaya akhir pada proyek konstruksi gedung.

[18]Sholahuddin, M., & Saputra, I. H. (2024). Penerapan Earned Value Management (EVM)

sebagai upaya pengendalian kinerja biaya dan waktu pelaksanaan pada pekerjaan infrastruktur

jalan.

[19]Simu, X. M. D., Irawan, D., Riman, & Cakrawala, M. (2025). Evaluasi kinerja biaya proyek

Rumah Sakit Wilayah Selatan Bojonegoro dengan Earned Value Management.

[20]Siva, H. A., & Junita, I. (2025). Evaluasi kinerja proyek perumahan rakyat di Kabupaten

Bandung Barat dengan menggunakan Earned Value Management (EVM) dan visualisasi kurva

S.

[21]Syahrir, Y., Jusmidah, & Haerianti. (2025). Evaluasi manajemen waktu dan biaya pada proyek

peningkatan ruas jalan paket 4 menggunakan metode Earned Value.

[22]Tangkeallo, N. V., Latupeirissa, J. E., & Tiyouw, H. C. P. (2024). Analisis biaya dan waktu

proyek konstruksi dengan metode Duration Cost Trade Off

Published

2026-10-16

How to Cite

krisna permana, deka yuda, Setiawan, H. P., & Iswanto, H. H. (2026). EVALUATION OF PROJECT COST AND SCHEDULE PERFORMANCE USING THE EARNED VALUE MANAGEMENT (EVM) METHOD AND GAP ANALYSIS: EVALUASI KINERJA BIAYA DAN WAKTU PROYEK DENGAN METODE EARNED VALUE MANAGEMENT (EVM) DAN GAP ANALYSIS. Jurnal Qua Teknika, 16(02), 1-9. https://doi.org/10.35457/quateknika.v16i02.5985