EVALUATION OF PROJECT COST AND SCHEDULE PERFORMANCE USING THE EARNED VALUE MANAGEMENT (EVM) METHOD AND GAP ANALYSIS
EVALUASI KINERJA BIAYA DAN WAKTU PROYEK DENGAN METODE EARNED VALUE MANAGEMENT (EVM) DAN GAP ANALYSIS
DOI:
https://doi.org/10.35457/quateknika.v16i02.5985Keywords:
Cost, Earned Value Management, Project Performance, ScheduleAbstract
Schedule delays and cost overruns are common problems in construction projects. This study evaluates the cost and schedule performance of a three-story boarding house construction project in Blitar City, with a contract value of IDR 1,408,700,000, using Earned Value Management (EVM) and Gap Analysis. EVM was used to measure project performance and project cost and schedule completion, while Gap Analysis identified deviations and critical work items. At week 23, actual progress reached 80%, with an SPI of 0.80 and CPI of 0.73, indicating schedule delay and cost inefficiency. The projected EAC was IDR 1,929,726,027, with an EAS of approximately 29 weeks. Concrete and masonry works were identified as critical factors, contributing 52.25% of the project weight. After simulating corrective actions through weekly monitoring, additional personnel, and limited overtime, progress increased to 95%, with SPI and CPI reaching 0.95 and EAS decreasing to approximately 24.21 weeks. The results demonstrate that integrating EVM and Gap Analysis is effective for detecting project deviations and determining appropriate corrective actions.
Downloads
References
[1] Aditama, R., & Witjaksana, B. (2021). Analisis biaya dan waktu menggunakan metode EVM
(Earned Value Method): Studi kasus pada proyek pembangunan Gedung Laundry RSUD
Sidoarjo.
[2] Annas, F. M., Solikin, M., Harnaeni, S. R., & Sunarjono, S. (2021). Evaluasi kinerja biaya dan
waktu pelaksanaan menggunakan metode Earned Value (EVM): Studi kasus Proyek
Pengendalian Banjir Kali Lamong.
[3] Asyiah, S., Maddeppungeng, A., & Alfalakh, D. S. (2020). Evaluasi kepuasan pelanggan
terhadap kinerja manajemen proyek kontraktor besar: Studi kasus Proyek Pembangunan
Kampus Untirta Sindangsari.
[4] Dharmawan, R. D., Safarizki, H. A., & Firdausi, A. A. (2023). Evaluasi efektivitas keputusan
addendum proyek terhadap waktu pekerjaan proyek berbasis Earned Value Method.
[5] Erik, D., Rodhi, N. N., Saputra, I. H., & Sholahuddin, M. (2025). Evaluasi kinerja biaya dan
waktu pada proyek jembatan menggunakan metode Earned Value: Studi kasus rehabilitasi
Jembatan Ngaglik Kedungadem-Kepohkidul Kabupaten Bojonegoro.
[6] Hayati, N. I., & Lugi, D. (2020). Evaluasi biaya dan waktu dengan metode Earned Value
Management: Studi kasus Ruko Damara Village, Kelurahan Ciparigi, Kota Bogor.
[7] Honesti, L., & Wiranto, R. (2021). Analisis pelaksanaan proyek konstruksi dengan metode
Earned Value pada pembangunan Hotel Santika Bukittinggi.
[8] Jatnika, A., & Johari, G. J. (2019). Analisis pengendalian waktu dengan Earned Value Concept
pembangunan Rumah Susun Jawa Barat 2 TA. 2019 Universitas Garut.
[9] Madeppungeng, A., Intari, D. E., & Fauziah, N. N. (2020). Evaluasi kepuasan pelanggan
terhadap kinerja manajemen proyek kontraktor besar: Studi kasus proyek pembangunan
Bendungan KLM di Provinsi Banten.
[10]Maulia, S., Maskur, A., & Hartati, G. (2025). Evaluasi pengendalian waktu menggunakan
metode Earned Value Management (EVM) pada pembangunan sarana dan prasarana Gedung
Pemuda Juara Kabupaten Pangandaran.
[11]Pasolang, R., & Mangngenre, S. (2025). Evaluasi kinerja proyek Feed End Shell Dryer
Replacement Process Plant PT. A menggunakan metode Earned Value Management.
[12]Purwanto, S., Mu’min, M. A., & Fernanda, A. (2021). Analisis nilai hasil terhadap waktu pada
proyek RS Hermina Kutabumi Tangerang.
[13]Putri, R. T., Damayanti, S., & Dofir, A. (2023). Analisis faktor penyebab keterlambatan
penyelesaian pada proyek Pembangunan Apartemen Urban Signature Ciracas.
[14]Rafi, M., & Hidayat, M. (2024). Evaluasi biaya dan waktu menggunakan metode EVM
(Earned Value Management).
[15]Rizki, Y., Imran, R. A., Muhammad, K., Kusuma, H. I., & Ridho, A. F. (2024). Usulan
penerapan Contractor Safety Management System pada tahap pra kualifikasi di PT. UES
menggunakan Gap Analysis.
[16]Rudiantoro, A. T. S. (2020). Evaluasi pengendalian biaya proyek peningkatan Jalan
Margaluyu Tahap II (DAK) dengan metode Earned Value Management (EVM).
[17]Sari, M. M., Hadi, T. S., & Aldiansyah. (2020). Faktor penyebab pembengkakan biaya yang
berpengaruh terhadap biaya akhir pada proyek konstruksi gedung.
[18]Sholahuddin, M., & Saputra, I. H. (2024). Penerapan Earned Value Management (EVM)
sebagai upaya pengendalian kinerja biaya dan waktu pelaksanaan pada pekerjaan infrastruktur
jalan.
[19]Simu, X. M. D., Irawan, D., Riman, & Cakrawala, M. (2025). Evaluasi kinerja biaya proyek
Rumah Sakit Wilayah Selatan Bojonegoro dengan Earned Value Management.
[20]Siva, H. A., & Junita, I. (2025). Evaluasi kinerja proyek perumahan rakyat di Kabupaten
Bandung Barat dengan menggunakan Earned Value Management (EVM) dan visualisasi kurva
S.
[21]Syahrir, Y., Jusmidah, & Haerianti. (2025). Evaluasi manajemen waktu dan biaya pada proyek
peningkatan ruas jalan paket 4 menggunakan metode Earned Value.
[22]Tangkeallo, N. V., Latupeirissa, J. E., & Tiyouw, H. C. P. (2024). Analisis biaya dan waktu
proyek konstruksi dengan metode Duration Cost Trade Off
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Jurnal Qua Teknika

This work is licensed under a Creative Commons Attribution-ShareAlike 4.0 International License.
Authors who publish with this journal agree to the following terms:
- Copyright on any article is retained by the author(s).
- Author grant the journal, right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work’s authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal’s published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.
- The article and any associated published material is distributed under the Creative Commons Attribution-ShareAlike 4.0 International License