REKAYASA NILAI PEMBUATAN TERHADAP WAKTU DAN SPESIFIKASI PEKERJA PADA PEMBANGUNAN PERUMAHAN PESONA TUGU RANTE RESIDENCE TYPE 45 KABUPATEN BLITAR
Abstract
due torecent economic situation, contractors have een required to be able to minimize cost and the same time to also maintain the quality of the project. One of the methods that can be apllied as an alternative to achieve it is value engineering. The aim of this studyis to apply this method in a construction project. The construction project of
Housing development in charm tugu rante type 45 residence district blitar Rp 99,792,000.00
Value engineering method consist of 4 ( five ) phases. It covers information phase, which contains of identification of the high-cost work and the unnecessary cost ( function analysis ); creative phase; analyzing phase which includes the selection of alternative dealing with the analysis of its benefit and cost, it project life cycle cost and the selection of alternatives by using AHP method; and Recommendation phase.
By implementing thismethod,the project cost can be minimized in 5 area of wark,woll work Rp1,902,459,wall strucco work Rp3,941,693,the work of the faundotion stone,soil excavation Rp211,616,excavation work Rp782,012,ceramic work Rp294,775. Thus total reduction cost that be achieved by using this method is upto
Authors who publish with this journal agree to the following terms:
- Copyright on any article is retained by the author(s).
- Author grant the journal, right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work’s authorship and initial publication in this journal.
- Authors are able to enter into separate, additional contractual arrangements for the non-exclusive distribution of the journal’s published version of the work (e.g., post it to an institutional repository or publish it in a book), with an acknowledgement of its initial publication in this journal.
- Authors are permitted and encouraged to post their work online (e.g., in institutional repositories or on their website) prior to and during the submission process, as it can lead to productive exchanges, as well as earlier and greater citation of published work.
- The article and any associated published material is distributed under the Creative Commons Attribution-ShareAlike 4.0 International License